Timeline
Project Timelines
Public Works
Current Step: Site Design - Master Planning Next Step: Site Design - Schematic Design
The City owns just over 15 acres at 6100 and 6110 Olson Memorial Hwy for the future public works campus. The City hopes to have the Public Works facility completed in 2029.
Public Safety & Civic Center Campus
Current Step: Site Design - Master Planning Next Step: Site Design - Schematic Design
The City is currently planning the campus with Hennepin County. The City hopes to have the Civic Center Campus construction completed by 2031.
East Fire Station
Current Step: Site Design - Master Planning Next Step: Site Design - Schematic Design
The City is currently working on Site Design with Leo A Daly and SEH, Inc. The City hopes to have the new East Fire Station completed in 2028.
About the Project Phases
There are several key steps when it comes to building a new public facility. They can broadly be broken down into the following:
1.
Site Acquisition
Site acquisition is the process of identifying, evaluating, and securing land suitable for the project.
2.
Site Design
Once a site has been selected and acquired, the City can move into the site design process. The City publishes a Request for Proposal (RFP) to seek qualified firms to design the site. Once selected, architects and engineers create detailed plans for the facility. The design phase may have multiple phases, including:
Design Team Selection: Selecting a firm to create a design for a project
Master Planning: Developing an overall building and site concept
Schematic Design: Creating building and site architectural designs
Design Development: Refining of conceptual design and developing construction methods
Construction Documents: Illustrating exact project design specifications and outlining expectations for the contractor
3.
Site Preparation
After the site design is complete, the land is cleared and made ready for construction. This can involve demolition, grading, utility relocation, and environmental mitigation.
4.
Bidding
At this point, the project is put out to bid for contractors to submit proposals. Bids are reviewed based on cost, qualifications, and compliance with public procurement laws.
5.
Building
Once all prior steps have been complete, construction may begin, following the approved design and schedule. This includes ongoing inspections, quality control, and eventual commissioning of the facility for public use.
Milestones
-
November 17, 2026 - The City Council will consider contracts for the Public Works construction manager at risk (CMAR) and architect/engineer.
November 4, 2026 - The City Council approved a contract for a commissioning agent, IMEG, for the East Fire Station.
August 1, 2026 - The City acquired 6110 Olson Memorial Hwy, the second of two properties needed for its future public works campus. The 15-acre campus also includes 6100 Olson Memorial Hwy.
July 7, 2026 - The City hired Leo A Daly to design the East Fire Station, Terra Construction as a construction manager at risk (CMAR), and SEH, Inc. to design and reconstruct Lilac Drive.
July 7, 2026 - The City hired Goff Public to assist with strategic communications for Building Forward.
May 2026 - The Golden Valley Fire Station Bonding Request passed in the Omnibus Bonding Bill, awarding the City an additional $2 million to construct, equip, and furnish a new east fire station.
May 1, 2026 - The City took ownership of 1875 Lilac Drive, the home of the future East Fire Station.
February 17, 2026 - The City hired Tegra Group, Inc. for Owner’s Representation Services.
-
Dec 16, 2025 - The City hired Perkins & Will to lead the Civic Center Campus Master Planning effort.
Dec 8, 2025 - The City took ownership of 6100 Olson Memorial Highway, half of the site for the future Public Works campus.
Sept 2025 - Space Needs Assessment updated with BKV, who assisted with the Municipal Facilities Master Plan Study completed in 2021.
-
April 1, 2024 - Local Sales Tax went into effect.
-
Dec 19, 2023 - Local Sales Tax ordinance passed.
Nov 7, 2023 - Golden Valley voters approved three ballot questions for a 1.25% local sales tax to fund the City’s Building Forward Plan.
City received $3.172 million in grant funding to support the East Fire Station project.
-
Dec 2021 - Municipal Facilities Master Plan Study completed. The study combined the City’s long-term goals and needs assessments to create plans for the future of downtown Golden Valley and its facilities.
Sept 2021 - the Facilities Study Task Force presented recommendations to the City Council for redeveloping City-owned facilities, which included how to best address the shortcomings of the Public Works and Public Safety buildings.
-
The City created the Facilities Study Task Force to further explore ways its public buildings could best serve the community and create new development opportunities in downtown Golden Valley. Throughout 2020 and 2021, the Facilities Study Task Force engaged the Golden Valley community and gathered input through surveys, a virtual open house and a virtual forum, and meetings with downtown businesses, civic organizations, and various local groups. The Facilities Study Task Force—made up of residents, business leaders, City staff, and a Planning Commission representative—laid the groundwork for development of a long-term plan to address the City’s building needs.